試卷年份2014年上半年
試題題型【單選題】
試題內(nèi)容

In project management , a ( 1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2 ) ,budget and duration, linked by dependencies and scheduled events.
(1)A. schedule               
B. activity                 
C. plan            
D. contractor
(2)A. finding                   
B. balance      
C. allocation   
D. distribution

查看答案