Through a formula  that  uses  attributes, a  project  manager  estimates  a new  project’s cost and duration from a combination of quantified project attributes. The project manager uses which of the following estimation techniques?
	A、Parametric estimating
	B、Analogous estimating
	C、Reserve estimating
	D、Expert judgment