You are project manager for a strategic project with a multi-million dollars value assigned by a company that is listed at a US stock exchange. Recent earned value analysis after app 25% completion told you that your project has a CPI of 0.76.What should the project manager do right now
	A、The variance is a signal of a sound project which is well under budget. There is no need for action.
	B、A project that much under budget may be a problem for negotiating future budgets. Try to spend money somewhere else.
	C、 You should immediately inform your management, which should then assess whether this CPI constitutes a material financial issue.
	D、 It is still early in the project and data are yet inaccurate. Wait a while and allow numbers from the project to stabilize.
                    
 10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
 免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
 全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
 信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
 信管老師100小時(shí)直播課程
 軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
 中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
 系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
 軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題