試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The member monitoring the processes looks at the product’s control chart. There are six consecutive points below the mean, but within control limits. The project manager should take which of the following actions?
A、Adjust the process.
B、Create an Ishikawa diagram.
C、Conduct a Design of Experiments.
D、No action is required.