午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線(xiàn)考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The member monitoring the processes looks at the product’s control chart. There are six consecutive points below the mean, but within control limits. The project manager should take which of the following actions?
A、Adjust the process.
B、Create an Ishikawa diagram.
C、Conduct a Design of Experiments.
D、No action is required.


相關(guān)試題

推薦文章