試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager is in the process of documenting the results of a team member’s work to ensure that the team member has met all of the requirements and specifications. What is the project manager actually doing ?
A、Performing administrative closure activities.
B、Completing lessons learned.
C、Completing the requirements specification document.
D、Updating the issues log.