試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A company has several high-priority projects. However, the company did not provide enough resources available to work on all of their project activities. What should the line managers and the project managers do ?
A、Set up a meeting and negotiate resource allocations.
B、Assign resources on a first-come, first-serve basis.
C、Allocate resources to work extra hours on multiple projects.
D、Create a matrix of virtual teams with existing resources.