試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The director of the business unit submits a request for a new software application. The project manager determines the need for project requirements gathering and scope developments. Which of the following activities should be performed ?
A、Create the technical specification and requirement traceability matrix.
B、Create issue log and perform risk analysis.
C、Document a product description and create a list of stakeholders.
D、Draft the current and future processes and draft the work breakdown structure.