午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Diagram shows the sequence of activities for project xyz and its duration, The project manager is asked to reduce the project duration by two weeks, None of the activities can be fast tracked. Activities A and F cannot be crashed; activity G can be crashed by two weeks; and all other activities can be crashed by one week.To meet the new project duration requirement, which of the following will the project manager decide to do?

A、Crash activity G

B、Crash activities C and D

C、Crash activities G and C and D

D、Crash activities G and F and C


相關(guān)試題

推薦文章