午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager provides senior management with a status report. The project manager has developed a CPM diagram showing two activities with negative total slack.Which of the following conclusions can management derive from this analysis?
A、The two activities are critical activities of the project
B、The project manager has miscalculated because it is possible to have at most one activity with negative slack
C、Late finish is less than late start for both activities
D、The project is progressing ahead of schedule since there are already activities with negative slack


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容