試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The team members move onto new projects. The project manager moves onto a different project in the organization, White checking the status of the organization’s projects. the project management office notices the contracts for that project were not closed properly. The project manager is asked to correct the issue. Which of the following should the project manager review?
A、Records management system
B、Scope management plan
C、Procurement audits
D、Validate scope