午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager for a construction project acquires the approval on a change order to provide additional concrete foundations. This change is analyzed using a Monte Carlo simulation but weather conditions are overlooked. Also, the risk of physical harm to the team members performing the outdoor work was not considered, The project must be finished on time, as part of the foundation for venue of a local festival.What should the project manager do next?
A、Accept that the project goes into default, and pay the price for not finishing scope on time as stipulated in the contract
B、Stick to the original plan and reversal procedure
C、Consult the project sponsor and meet with the major stakeholders to look for alternatives
D、Keep this new knowledge within the project team, and hope for a change in temperature that will allow completion of the project


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容