試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The development of a new software application had been completed on time and within budget although resources were new to the technology. During the code install, it was determined that certain aspects of the hardware needed to be configured before the new application could be utilized. The customer was incredibly upset and disappointed as this would cause a delay in the implementation. What could have been the cause for this situation?
A、The customer did not request the hardware to be appropriately set up.
B、The hardware configuration was too expensive and would have caused the project to run over budget.
C、A work breakdown structure was not created adequately.
D、The resources completed a three-week training course versus a more through six-week training course.