試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At the conclusion of a project, there is a compilation of information that serves as the memory and history of the project. That document evaluates the overall success of the project including its strengths and weakness, organization and techniques used to get results.What is the collection of information called?
A、Stakeholder feed back
B、Post-implementation audit
C、Lesson learned
D、Final project report