午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A Team member was recently promoted as project manager and has been assigned a $2million. The department manager schedules a meeting to review the project charter within two weeks.What should the project manager do next?
A、Create the project scope statement.
B、Meet with the sponsor to define the business needs.
C、Schedule a kick-off meeting with team members.
D、Review the project management plans with the stakeholders.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容