午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

After project starts, a senior stakeholder requests that another deliverable be added. The project sponsor previously stated that no further funding would be available for this project. What should project manager do?
A、Ask the project team make a joint agreement to ask for more funding
B、Present the projects scope statement and reject the new request
C、Reject the new request to stop any further information gathering
D、Ask for a formal change request containing all required information


相關試題

推薦文章
合作網(wǎng)站內(nèi)容