A project manager uses a schedule network analysis technique in which a distribution range of probable activity durations is defined for each activity. Which of the following techniques should the project manager use to calculate a distribution of possible outcomes for the total project?
	A、Resource leveling
	B、Monte Carlo analysis
	C、Critical Chain technique
	D、Cause and effect analysis