A project is behind schedule and over budget. The root cause of the issue is that the engineer added functionality into the design, per the customer's written e-mail, on which the project manager was copied. Which of the following could have prevented this is issue?
	A、Communication plan
	B、Risk management plan
	C、Project management plan
	D、Change control system