The company’s accounting system project is close to the end of its execution phase when the finance director discovers an important requirement is missing, and instructs the project manager to immediately implement the change. If the project deliverable is produced according to the current specification, it will not be usable. The change is significant, but the project manager could possibly meet the project deadline, if the work is started immediately. What should the project manager do first?
A、Call the project sponsor and ask if the finance director is authorized to order changes to the project scope.
B、Explain to the finance manager that the change may delay the project beyond the deadline.
C、Start processing the request according to the project’s change management plan
D、Estimate, plan, and implement the change in order to not lose time during the change request process.
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。