試卷年份2019年下半年
試題題型【單選題】
試題內(nèi)容

 The information security management system preserves the confidentiality ,integrity and availability of information by applying a/an(  ) management process and gives confidence to interested parties.
A.quality
B.information
C.risk
D.data


查看答案

相關(guān)試題

69題: ()不適合作為項(xiàng)目監(jiān)理例會(huì)的主要議題。
A、分包單位的管理和協(xié)調(diào)問題
B、項(xiàng)目款支付的核定問題
C、因突發(fā)性變更事件引起的進(jìn)度問題
D、針對(duì)存在的質(zhì)量問題提出改進(jìn)措施要求
答案解析與討論:www.xomuzic.com/st/4205014133.html

21題: (  )是指導(dǎo)整個(gè)項(xiàng)目執(zhí)行和控制的文件。
A.項(xiàng)目計(jì)劃
B.資源規(guī)劃
C.工作說明書
D.質(zhì)量計(jì)劃

答案解析與討論:www.xomuzic.com/st/1102077178.html

22題: ( )concerns a cycle of organizational activity:the acquisition of information from one or more sources , the custodianship and the distribution of that information to those who need it ,and its ultimate disposition through archiving or deletion.
A.Acquisition management
B.Information management
C.Distrbution management
D.Deletion management

答案解析與討論:www.xomuzic.com/st/11020826054.html

24題: (  )describes the configurable items of the project and identifies the items that will be recorded and updated so that the product of the project remains consistent and operable.
A.The configuration management plan
B.The change management plan 
C.The requirements traceability matrix
D.The change baseline
答案解析與討論:www.xomuzic.com/st/11021023727.html

25題: When required, the Perform Integrated Change Control Process includes a(  ),which is a formally chartered group responsible for reviewing evaluating, approving, deferring or rejecting changes to the project and for recording and communicating such decisions
A.BBC 
B.CCB
C.BCB
D.CBC

答案解析與討論:www.xomuzic.com/st/110211829.html

26題: (  )are also known as tally sheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem They are especially useful for gathering attributes data while performing inspections to identify defects.
A.Effect sheets
B.Data sheets
C.Check sheets
D.Cost sheets