PMP?每日一練試題(2023/4/15)

PMP?當(dāng)天每日一練試題地址:www.xomuzic.com/exam/ExamDay.aspx?t1=33

往期PMP?每日一練試題匯總:www.xomuzic.com/class/27/e33_1.html

PMP?每日一練試題(2023/4/15)在線測試:www.xomuzic.com/exam/ExamDay.aspx?t1=33&day=2023/4/15

點(diǎn)擊查看:更多PMP?習(xí)題與指導(dǎo)

PMP?每日一練試題內(nèi)容(2023/4/15)

  • 試題1

    A project to implement a new system has trouble launching due to extensive and contradictory discussions regarding the project deliverables. The project manager leaves the company;and a new project manager is assigned to the task.
    What should be the first action for the new project manager?
    啟動(dòng)實(shí)施項(xiàng)目新系統(tǒng)時(shí)會(huì)遇到麻煩,由于對(duì)項(xiàng)目可交付成果的討論廣泛且矛盾。項(xiàng)目經(jīng)理離開公司,一個(gè)新的項(xiàng)目經(jīng)理接手這個(gè)任務(wù)。那么新的項(xiàng)目經(jīng)理首先應(yīng)該采取什么行動(dòng)?
    A、Formalize the project management plan and communicate this to relevant stakeholders
    正式確定項(xiàng)目管理計(jì)劃,并傳達(dá)給相關(guān)利益方
    B、Escalate to the project sponsor and request support in handling the ongoing discussions. 擴(kuò)大項(xiàng)目發(fā)起人,并請(qǐng)求支持處理正在進(jìn)行的討論。
    C、Develop a work breakdown structure and communicate this to all relevant stakeholders. 制定工作分解結(jié)構(gòu),并傳達(dá)給所有利益相關(guān)者
    D、Formalize a project charter and request approval from the sponsor and key stakeholders. 形成一套完整的項(xiàng)目章程,并且能夠得到項(xiàng)目發(fā)起人和關(guān)鍵利益相關(guān)者的支持

    查看答案

    試題參考答案:D

    試題解析與討論:www.xomuzic.com/st/4903512546.html

  • 試題2

    信息技術(shù)部將開發(fā)一個(gè)市場營銷部的接口程序,信息技術(shù)部經(jīng)理承諾近期交付接口程序。一名項(xiàng)目經(jīng)理和技術(shù)資源被分配到該項(xiàng)目上。項(xiàng)目經(jīng)理與團(tuán)隊(duì)開會(huì)討論,由于項(xiàng)目的高優(yōu)先級(jí),必須立即開始接口程序的相關(guān)工作。項(xiàng)目經(jīng)理首先應(yīng)該做什么?
    A、制定項(xiàng)目章程
    B、識(shí)別風(fēng)險(xiǎn)
    C、制訂溝通管理計(jì)劃
    D、制訂項(xiàng)目管理計(jì)劃

    查看答案

    試題參考答案:A

    試題解析與討論:www.xomuzic.com/st/4827927349.html

  • 試題3

    公司總裁擔(dān)心某次自然災(zāi)害對(duì)公司的影響,管理層應(yīng)如何識(shí)別需要應(yīng)用其資源并減輕潛在影響的領(lǐng)域
    A.制定并保留一份積極的風(fēng)險(xiǎn)登記冊(cè),八包含風(fēng)險(xiǎn)減輕戰(zhàn)略和成本效益分析
    B.根據(jù)定性風(fēng)險(xiǎn)分析和預(yù)期損失,制定并保留一份積極的風(fēng)險(xiǎn)登記冊(cè)
    C.讓每個(gè)開發(fā)團(tuán)隊(duì)在信息輻射器上張貼最高風(fēng)險(xiǎn)的開發(fā)項(xiàng)
    D.通過將開發(fā)團(tuán)隊(duì)分隔成兩個(gè)地方來避免風(fēng)險(xiǎn),確保知識(shí)持續(xù)性

    查看答案

    試題參考答案:C

    試題解析與討論:www.xomuzic.com/st/5301822003.html

  • 試題4

    一個(gè)風(fēng)險(xiǎn)是已經(jīng)記錄的,技術(shù)人員發(fā)現(xiàn)了,應(yīng)該怎樣來處理這個(gè)風(fēng)險(xiǎn)?
    A、按照風(fēng)險(xiǎn)管理計(jì)劃中的應(yīng)對(duì)計(jì)劃進(jìn)行應(yīng)對(duì)
    B、跟技術(shù)人員溝通風(fēng)險(xiǎn)情況
    C、討論不同的解決方案
    D、確認(rèn)目標(biāo)和資源

    查看答案

    試題參考答案:B

    試題解析與討論:www.xomuzic.com/st/476964372.html

  • 試題5

    項(xiàng)目經(jīng)理正在管理一個(gè)由跨職能團(tuán)隊(duì)執(zhí)行的軟件重新設(shè)計(jì)項(xiàng)目。該公司正在進(jìn)行敏捷轉(zhuǎn)型,項(xiàng)目管理辦公室(PMO)發(fā)布了更新后的政策和程序,要求當(dāng)前項(xiàng)目迭代開發(fā)整合到項(xiàng)目管理方法中。若要確保每次迭代交付都考慮質(zhì)量,項(xiàng)目經(jīng)理應(yīng)該怎么做?
    A.與相關(guān)方以及和項(xiàng)目團(tuán)隊(duì)合作,以確保有明確定義的“已完成”定義(DoD)
    B.將測試和驗(yàn)證活動(dòng)分配給具有功能背景的團(tuán)隊(duì)成員
    C.安排該項(xiàng)目最后一次迭代的所有測試活動(dòng),以便整個(gè)團(tuán)隊(duì)可以關(guān)注與同一目標(biāo)
    D.分配專門的軟件測試人員,以確保在整個(gè)項(xiàng)目生命周期中進(jìn)行測試

    查看答案

    試題參考答案:A

    試題解析與討論:www.xomuzic.com/st/5253722007.html

  • 試題6

    項(xiàng)目經(jīng)理計(jì)劃為一個(gè)工期覆蓋以后三年的施工項(xiàng)目采購混凝土。由于沒有足夠的當(dāng)?shù)厥袌鲂畔?,?xiàng)目經(jīng)理不能預(yù)測未來的混凝土價(jià)格趨勢。項(xiàng)目經(jīng)理應(yīng)該與混凝土供應(yīng)商簽訂哪種合同?
    A、總價(jià)加經(jīng)濟(jì)價(jià)格調(diào)整合同
    B、總價(jià)加激勵(lì)費(fèi)用合同
    C、成本加激勵(lì)費(fèi)用合同
    D、成本加固定費(fèi)用合同

    查看答案

    試題參考答案:A

    試題解析與討論:www.xomuzic.com/st/4888724155.html

  • 試題7

    考慮取消應(yīng)急儲(chǔ)備,是以下哪個(gè)工具和技術(shù)?
    A、風(fēng)險(xiǎn)再評(píng)估
    B、儲(chǔ)備分析
    C、應(yīng)急應(yīng)對(duì)策略
    D、接受

    查看答案

    試題參考答案:B

    試題解析與討論:www.xomuzic.com/st/4739029654.html

  • 試題8

    A contracted third-party vendor delivered one of the main components of the project during the execution phase. Although the vendor delivered on time,the project manager discovers t hat the component failed to meet the approved standards. Since the project is in its final phase of closure and handover,what should the project manager do?
    在執(zhí)行階段.一個(gè)已簽約的第三方供應(yīng)商交付了項(xiàng)目的主要組件之一。雖然該供應(yīng)商按時(shí)交付組件,但項(xiàng)目經(jīng)理發(fā)現(xiàn)該組件未能滿足批準(zhǔn)的標(biāo)準(zhǔn)。 由于項(xiàng)目處于收尾和移交的最終階段.項(xiàng)目經(jīng)理應(yīng)該做什么?
    A、Review the component's records and documents. 審查該組件的記錄和文件。
    B、Close the project with guidance from the project management office(PMO). 在項(xiàng)目管理辦公室(PMO)的指導(dǎo)下結(jié)束該項(xiàng)目。
    C、Note that the component failed of meet standards,communicate it to the vendor,and close the project. 將組件未能滿足標(biāo)準(zhǔn)記錄下來.將其傳達(dá)給供應(yīng)商.然后結(jié)束項(xiàng)目。
    D、Investigate the issue by referring to the formal acceptance of the vendor's work. 通過查閱對(duì)供應(yīng)商工作的正式驗(yàn)收文件來調(diào)查該問題。

    查看答案

    試題參考答案:D

    試題解析與討論:www.xomuzic.com/st/4807219510.html

  • 試題9

    為確保產(chǎn)品符合業(yè)務(wù)需求,敏捷項(xiàng)目經(jīng)理應(yīng)采取的其中一個(gè)首要步驟是什么?
    A.讓干系人的利益和期望相符合
    B.開始規(guī)劃一下次迭代
    C.集合開發(fā)人員,為用戶故事排列優(yōu)先級(jí)
    D.與開發(fā)團(tuán)隊(duì)一起制定項(xiàng)目計(jì)劃

    查看答案

    試題參考答案:A

    試題解析與討論:www.xomuzic.com/st/5305719398.html

  • 試題10

    某個(gè)按計(jì)劃應(yīng)該參加項(xiàng)目狀態(tài)評(píng)審會(huì)議的重要相關(guān)方. 最近出現(xiàn)了不明原因缺席會(huì)議的情況。這種情況應(yīng)該被記錄在以下哪個(gè)文件中?()
    A、風(fēng)險(xiǎn)登記冊(cè)
    B、問題日志
    C、變更日志
    D、組織過程資產(chǎn)

    查看答案

    試題參考答案:B

    試題解析與討論:www.xomuzic.com/st/495535853.html

信管網(wǎng)訂閱號(hào)

信管網(wǎng)視頻號(hào)

信管網(wǎng)抖音號(hào)

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評(píng)論  查看完整評(píng)論  

報(bào)考條件查詢

推薦文章

精選

課程

提問

評(píng)論

收藏