1、 ( )is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
信管網(wǎng)參考答案:D
查看解析:http://www.xomuzic.com/st/1314.html
(1)是關(guān)鍵路徑法中用于構(gòu)建項目進度網(wǎng)絡(luò)圖的方法,該網(wǎng)絡(luò)圖使用方框或矩形(稱為節(jié)點)來表示活動,并用箭頭將它們連接起來,箭頭表示它們之間存在的邏輯關(guān)系。
A、 珀特
B、 AOA公司
C、 世界銀行
D、 產(chǎn)品數(shù)據(jù)管理
72、 Schedule development can require the review and revision of duration estimates and resource estimates to create an approved( )that can serve as a baseline to track progress.
A.scope statement
B.a(chǎn)ctivity list
C.project charter
D.project schedule
信管網(wǎng)參考答案:D
查看解析:http://www.xomuzic.com/st/1315.html
進度計劃的制定可能需要對工期估算和資源估算進行審查和修訂,以創(chuàng)建一個可作為跟蹤進度基線的已批準(zhǔn)的()項目。
A、 范圍說明
B、 活動列表
C、 項目章程
D、 項目進度計劃
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |