An IT team sent out information on how to access a new tool adopted for project communications. Now some stakeholders are asking questions that lead the project manager to believe they are not leveraging the new tool. What should the project manager do?
IT團(tuán)隊(duì)之前發(fā)送了有關(guān)如何訪(fǎng)問(wèn)項(xiàng)目溝通所采用的新工具的信息。現(xiàn)在,一些相關(guān)方提出一些問(wèn)題,讓項(xiàng)目經(jīng)理認(rèn)為他們沒(méi)有利用新工具。項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.Abandon the new tool and revert to previous methods for communicating updates放棄新工具并恢復(fù)以前用于溝通更新的方法
B.Resend the information on how to access the new tool重新發(fā)送有關(guān)如何訪(fǎng)問(wèn)新工具的信息
C.Discuss these concerns with stakeholders and offer to provide training on the new tool與相關(guān)方討論這些問(wèn)題,并提供新工具的相關(guān)培訓(xùn)
D.meet with the IT team to obtain ideas on how to enforce the use of the new tool與IT團(tuán)隊(duì)開(kāi)會(huì),獲得有關(guān)如何強(qiáng)制使用新工具的想法
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
C是參考答案。通過(guò)與相關(guān)方溝通識(shí)別問(wèn)題的原因,以確定解決方案。其他選項(xiàng)是可能的做法,需要先評(píng)估分析原因,再采取行動(dòng)。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專(zhuān)業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專(zhuān)業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿(mǎn)足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
項(xiàng)目經(jīng)理在收尾一個(gè)項(xiàng)目時(shí)遇到問(wèn)題,因?yàn)橄嚓P(guān)方不接受
由于超出項(xiàng)目經(jīng)理控制的原因,項(xiàng)目落后于進(jìn)度,一名有
在項(xiàng)目執(zhí)行期間,由于行業(yè)趨勢(shì)下行和產(chǎn)品價(jià)格下降,客
在測(cè)試期間,一位團(tuán)隊(duì)成員將某個(gè)質(zhì)量缺陷升級(jí)上報(bào)給項(xiàng)
在新項(xiàng)目啟動(dòng)會(huì)議期間,因?yàn)轫?xiàng)目將需要采購(gòu)新設(shè)備,生
發(fā)表評(píng)論 查看完整評(píng)論 | |